A close-up of a printing press in operation, producing colorful printed sheets with images of vegetables. Metal rollers and guides ensure precise movement—an example of Continuous Improvement in manufacturing processes.

Improving Productivity and Decreasing Costs

CLIENT INDUSTRY: Packaging Manufacturer

SOLUTION: Operational Excellence, Supply Chain

Our client produced labels for consumer goods and food products. The company lacked the capacity to meet its customers’ volume and variety requirements. This demand was met with additional shifts and selective outsourcing.

The recent loss of large client orders and contractual penalties for late deliveries made, the company stood to lose money and orders if it could not meet promised delivery dates.

Business Challenge

The company needed to increase capacity without a large capital equipment investment. Greatly reducing the non-value added (NVA) time in the production process could provide the needed production capacity. One source of NVA time was relatively long changeover and setup times (in some cases more than three hours).

 Solution

  • CBS led a Kaizen event to analyze and improve the process
  • A team of employees was assembled. CBS trained the team on Lean Production tools, specifically, SMED – Single Minute Exchange of Dies and other quick setup/changeover techniques.
  • The team then observed several changeovers or “make readies.” All related process steps were listed and categorized as:
    • Value-add (VA) vs. Non-value add (NVA)
    • Internal (machine is running) or External (machine not running) events
  • The RCE team analyzed all of the data collected and formulated several recommendations. Once piloted, the team developed a final recommendation, and they developed a set of Make Ready procedures to support the recommendation

Results

  • The resulting recommendations reduce the average changeover by 60% – from 100 minutes to 39 minutes
  • The workforce was empowered to make informed decisions regarding their work areas and procedures
  • Enabled the plant to reduce weekend shifts and reduce the need for temporary workers
  • Cost avoidance of adding another press ($300 – 500K)

Latest Insights

  • Manufacturing leadership team reviewing WIP and flow metrics during a lean transformation.

    Why Lean Transformations Plateau

    Early lean gains are real, and so is the plateau that follows. Tim Christlieb explains why the constraint shifts from individual processes to the…

  • Plant manager reviewing flow and constraints with a supervisor on a manufacturing floor shows operational excellence leadership behavior in practice

    Operational Excellence Is a Leadership Behavior

    Operational systems perform to the standard leadership allows. Tim Christlieb examines the tolerated behaviors that make congestion structural, the floor signals that reveal a…

Sign up to receive our latest insights!

"*" indicates required fields

This field is for validation purposes and should be left unchanged.
Name*