Improving Productivity and Decreasing Costs

CLIENT INDUSTRY: Packaging Manufacturer

SOLUTION: Operational Excellence, Supply Chain

Our client produced labels for consumer goods and food products. The company lacked the capacity to meet its customers’ volume and variety requirements. This demand was met with additional shifts and selective outsourcing.

The recent loss of large client orders and contractual penalties for late deliveries made, the company stood to lose money and orders if it could not meet promised delivery dates.

Business Challenge

The company needed to increase capacity without a large capital equipment investment. Greatly reducing the non-value added (NVA) time in the production process could provide the needed production capacity. One source of NVA time was relatively long changeover and setup times (in some cases more than three hours).

 Solution

  • CBS led a Kaizen event to analyze and improve the process
  • A team of employees was assembled. CBS trained the team on Lean Production tools, specifically, SMED – Single Minute Exchange of Dies and other quick setup/changeover techniques.
  • The team then observed several changeovers or “make readies.” All related process steps were listed and categorized as:
    • Value-add (VA) vs. Non-value add (NVA)
    • Internal (machine is running) or External (machine not running) events
  • The RCE team analyzed all of the data collected and formulated several recommendations. Once piloted, the team developed a final recommendation, and they developed a set of Make Ready procedures to support the recommendation

Results

  • The resulting recommendations reduce the average changeover by 60% – from 100 minutes to 39 minutes
  • The workforce was empowered to make informed decisions regarding their work areas and procedures
  • Enabled the plant to reduce weekend shifts and reduce the need for temporary workers
  • Cost avoidance of adding another press ($300 – 500K)

Download the PDF

 

Latest Insights

When one of our clients recognized the extent to which rising inefficiencies were affecting their business processes, the client reached out to the CBS experts for help. In just a matter of months, the results speak for themselves: a significant bump in all relevant KPIs, with several areas improving as much as 93%.

After years of cost cutting and loss of experienced “Tribal” manufacturing knowledge, a CBS aerospace client was not able to support increasing customer demand. Though they continued to make promises to return to on-time delivery, they continued to run 9 months delinquent to customer demand. Based on our prompt assessment of the situation, CBS developed and implemented an improvement plan that brought the client back to on-time and full condition.