A Stalled Plant Back on Track in Two Months
A family-owned manufacturer was sold into private equity, kept its gains from our first lean engagement, then stopped improving. We came back and got it on track in about two months.
By Keith Yeater
At a glance
On-time delivery went from under 60% to over 93%, and average manufacturing lead time went from more than six weeks to under three, in less than two months.
Through our People and Performance practice, we placed an interim plant manager in the operation in July to coach the existing plant manager. By October, we were handing the facility back to the skilled up plant manager with the goals met.
| Measure | Before | After |
|---|---|---|
| On-time delivery | Under 60% | Over 93% |
| Average manufacturing lead time | Over 6 weeks | Under 3 weeks |
| Output on the highest-volume line | About 4,000 units per hour | Over 6,000 units per hour |
| Daily sales and operations sync | Over 60 minutes | About 15 minutes |
| Staffing method | Set by feel | Calculated from forecast demand |
The situation
This was a family-owned, profitable business. It made good money for its owners. Then the owner sold it to a private equity portfolio company, and the bar changed. The business had never been built to deliver at the pace a private equity owner expects.
We were first brought in to set up the business and manufacturing processes utilizing a lean system. We spent about six months working side by side with the plant manager running improvement events and putting in cells. Then we left as planned. That’s what should happen when an engagement is done well. The goal is for the company to run it without us.
After we left, the plant got a little better and then stopped getting better. They were falling behind on customer orders, and lead times drifted past where customers needed them. The CEO called us back, this time through our People and Performance practice.
The problem
The CEO gave us three targets:
- Cut lead time from the customer’s order to the delivered part
- Improve gross margin
- Clear the past-due backlog
The KPIs we put in place during the first engagement had been dropped. The team had decided to stop tracking them. So before we changed anything, we rebuilt them and went back far enough to see what had actually happened. The data told us something more specific than “performance went down.”
The team had kept every gain from the first engagement. Nothing had slid backward. But nothing had moved forward either. In a working continuous improvement environment, output climbs a little every week because you’re improving something a little every day. This plant had plateaued.
The processes we laid out should have kept the gains coming. They were in place on paper, but the leadership team had never fully embraced them and led an organization in this fashion, so they never produced the results they were built to produce. That’s not a process design problem. It’s an adoption problem, and you can’t see it once you stop tracking the numbers.
The approach
We put an interim plant manager in the facility to coach and work alongside the existing plant manager. Not a replacement and not an auditor, but someone standing next to the person doing the job.
Let the cost structure set the order of work. We sat down with the CFO and went through the real financial numbers, not just the operations metrics. That review showed labor was a small share of the total cost of the product, and that one fact changed the plan. The usual move, squeezing labor efficiency first, would have been the wrong one. Customers were waiting and unhappy, and the fastest way out was more output, not cheaper output.
“The game was not to maximize labor right away. The game was to increase output so our customers got their parts.”
Clear the backlog first. We worked with senior leadership to bring in temporary workers for a short stretch and run the plant on roughly 20% overtime. Against total product cost, the expense was small. We could have worked only on the processes and let the backlog clear over a couple of months. It would have happened. But getting customers happy right away was worth more than the overtime bill. It also meant the team wasn’t chasing past-due orders all day, so it had room to improve.
Focus on the parts that carry the business. At the same time, we went after the processes behind the volume. Roughly 40 part numbers out of about 6,000 accounted for more than 80% of output; about 1%. Getting those 40 flowing through the plant took care of most of the customer complaints and most of the gross margin at once.
What we put in place
These are the four tools the plant now runs on.
Training Within Industry. The harder jobs got structured, step-by-step training so operators understood how to do the work, instead of picking it up by watching someone else.
Daily accountability. Every day, from the plant manager down to the operator, we held each other accountable. When a machine wasn’t running, why wasn’t it running, and what were we doing about it? Accountable doesn’t mean we yelled or scolded anyone. It meant asking questions and building the understanding that customers were depending on those machines. A lot of people on the floor didn’t know where the business stood when we got there. Once we told them, they didn’t want to be in that position either. They rallied around it and became part of the fix.
Demand-based staffing. Headcount had been set by instinct: “I think I need 20 people. Maybe 15.” We replaced that with arithmetic. Here is the work on the books, here are the hours available in the week, here is the crew that matches. The plant now forecasts weekly demand and staffs to it.
A better measure. The plant had been run on a crude count of output per hour, which swings with whatever products happen to be running that week. We moved it to an efficiency measure that takes product mix and variation out of the number, so it shows how the plant is actually performing.
Results
On-time delivery moved from under 60% to over 93%. People ask why that took two months. The reason is that every late order you ship still counts as late. Until you clean out the past-due backlog, on-time delivery isn’t going to improve. Once you do, it climbs fast.
Average manufacturing lead time dropped from over six weeks to under three. The plant now routinely takes an order and ships it inside the window customers need. Longer lead times remain only where the customer wants the order dated later.
Output rose across the lines we focused on. On the highest-volume line, hourly output went from about 4,000 units to over 6,000.
Our daily sales and operations sync ran well over an hour at the start, while we were still getting our arms around the problems. It’s now about fifteen minutes. We put the charts up, ask if anyone has concerns, the sales team says things are going well, and we get off the call. It went from Rome is burning to things are going pretty well, let’s move on to the next thing.
June was a struggle. July was much better. August was outstanding. We were well down the path of recovery by the end of July. From mid-August, we shifted from recovery to building processes the business can keep improving on its own. Now, going into October, we’re pulling ourselves out because we’ve met our goals.
What this manufacturing turnaround taught us
It’s all about managing the process: understanding the issue, communicating with the people, getting everybody involved, and holding everyone accountable every day. A few things I’d pass on to any leader whose plant has flattened out:
- Keep measuring. Without the KPIs, a plateau looks like stability until customers start complaining.
- Check adoption before redesign. Processes that leaders don’t run every day won’t produce results, however well they were designed.
- Let the cost structure set the order of work. When labor is a small share of product cost, spending a little more on it can be the fastest path to happy customers.
- Find the vital few. A small set of part numbers usually decides the month. Start there.